33 Girders

15 Days precast production

2 Days precast installation

Battle River Bridge

Ponoka, Alberta
Precast Manufacturer

In 2016 Eagle Builders was procured to engineer, manufacture, and deliver thirty-three precast concrete SLC 700 bridge girders. Various lengths between fourteen and twenty meters were used to compose the three-span bridge. Saving time and costs it took a total of 15 days for eagle builders to manufacture the entire scope of work. The largest girder weighed 92,000 lbs.

Replacing the original bridge of over 100 years old, this structure significantly improved the logistics of Ponoka enabling a new route for vehicles of up to eighty tonnes to deliver products and services.


“Largest girder weighed 92,000 lbs”

“14m & 20m length girders”