1757 Precast Pieces

2034 Parking Stalls

4 Levels

FOOTHILLS MEDICAL CENTRE PARKADE

Calgary, Alberta
Structural Contractor

The Parkade was awarded to Eagle Builders at the end of 2016 by a general contractor on behalf of Alberta Health Services. The project consists of 2034 parking stalls in 4 levels with 7 months of dedicated production and 8 months of on-site precast concrete installation. Eagle Builders is still manufacturing inverted tees, double tees, columns, spandrel panels, and wall panels to continue the ongoing supply and installation schedules.

The parkade consists of many precast concrete components including: inverted tees, double tees, columns, spandrel panels and wall panels.